Civil Works
Slabs, Trusses, Frames installed
External cladding and roofing
Internal linings
Final fixes & landscaping
settlement & handover
Site Timeline
What we have completed
Settlement
July 31 2023Titles and CCC issued
July 2023Landscaping complete
June 2023Practical Completion
May 2023Bathroom and kitchen fit-out, carpets and flooring done.
May 2023Internal linings and painting complete
April 2023External painting and brick works complete
March 2023Stair install, plumbing preline, oblique weatherboard construction
February 2023External Brick and Roofing
January 2023Truss construction, stair and window measure
December 2022Midfloor joist and board construction
November 2022Ground floor framing
November 2022Driveway concrete poured
November 2022Concrete slabs poured
October 2022Underslab / drainage constructions
October 2022Installing storm water tanks and retaining walls
September 2022Civil ground works started
August 2022Resource consent granted
August 2022Building consent granted
July 2022Engineering approval granted
May 2022House removal
March 2022