Stage 1

Civil Works

Stage 2

Slabs, Trusses, Frames installed

Stage 3

External cladding and roofing

Stage 4

Internal linings

Stage 5

Final fixes & landscaping

Stage 6

settlement & handover

Latest Site Footage

Professional Photos

Site Timeline

What we have completed

6

Settlement

July 31 2023
6

Titles and CCC issued

July 2023
6

Landscaping complete

June 2023
6

Practical Completion

May 2023
6

Bathroom and kitchen fit-out, carpets and flooring done.

May 2023
6

Internal linings and painting complete

April 2023
6

External painting and brick works complete

March 2023
6

Stair install, plumbing preline, oblique weatherboard construction

February 2023
6

External Brick and Roofing

January 2023
6

Truss construction, stair and window measure

December 2022
6

Midfloor joist and board construction

November 2022
6

Ground floor framing

November 2022
6

Driveway concrete poured

November 2022
6

Concrete slabs poured

October 2022
6

Underslab / drainage constructions

October 2022
6

Installing storm water tanks and retaining walls

September 2022
6

Civil ground works started

August 2022
6

Resource consent granted

August 2022
6

Building consent granted

July 2022
6

Engineering approval granted

May 2022
6

House removal

March 2022